Case study · Portico Group · For program and project leaders

A rebuilt Smartsheet setup made the land record hold up and the reports build themselves.

Book a free 30-minute assessment With Michael Ortiz. No pitch.
  • No more hand assembly: the twice-weekly client reports, often rebuilt after hours before, now build themselves

  • One set of names: landowner names from three trackers consolidated, every decision logged

  • Clean revocation: access lives in the Work App, so it can be removed in one place

land tracts under management
1,000s
land tracts under management · across multiple states
fewer columns per tracker
~85%
fewer columns per tracker · after the rebuild
of the client roll-up rebuilt from the new model
100%
of the client roll-up rebuilt from the new model · matched cell by cell
roles, each editing only its own milestones
10
roles, each editing only its own milestones · one view per role

Fix the reporting first, so the pain stops. Then rebuild underneath at a pace the team can absorb.

The challenge

Every contact with a landowner is a legal record. On a program heading toward condemnation cases, those notes and their dates can become evidence. The setup, built fast under pressure, got the program moving, but couldn’t carry that weight.

Our approach

We re-architected it: one register of record, one project plan template, and role-based views where people actually work. Nothing went big-bang: the old environment keeps running, untouched, until the team is ready to retire it, and the two are reconciled before anything is switched off. On the pilot tracts, the only differences were a couple of known quirks in the source data.

The same work was tracked in several places, and nobody could say which was right

  • Tract IDs typed by hand; one tract, many versions

    One register: One row per tract; reporting and GIS read from it

  • A column for every milestone in one wide tracker

    Project plans: Milestones as rows, not columns

  • Quality checks meant line-by-line review

    Exception queue: Formulas flag what’s late, overdue, blocked, or missing

Dates were stored as text, so turnaround time couldn’t be calculated at all.

Client
National engineering and infrastructure firm
Program
Federal land acquisition across several states, two-year runway
Platform
Smartsheet · Work App · Dynamic views · Data Shuttle · Data Mesh · API
Users
Land agents · Analysts · QC · Document team · Program leads · Partners
Status
Pilot built and validated, rolling out in phases

Each tracker now stays far from the platform’s cell limit

Columns per tracker

Before: one wide tracker
200+
After: one project plan
~30

The old tracker was closing in on the limit before the program was half done. Now a new project is a new sheet, so capacity grows with the program.

Update once. Everything downstream follows.

Has your Smartsheet setup outgrown itself?

Book a free 30-minute operational assessment. No pitch. Just an honest look at where you are and what to do next.