Case study · Portico Group · For leaders planning a move or big change

One command center moved a warehouse and office on time, with orders still shipping.

Book a free 30-minute assessment With Michael Ortiz. No pitch.
  • Orders kept shipping: from the new building while the old one was emptied

  • A live budget: every quote, bid and signed amount, with a low and high case, so the cash picture was always current

  • One RAID log: every risk, issue and decision logged with an owner and a date

old building handed back
On time
old building handed back · on schedule
smaller footprint
~40%
smaller footprint · sized to what the business needs
net cash from the lease agreements
+$890K
net cash from the lease agreements · more than the move cost
sprinkler upgrade avoided
~$500K
sprinkler upgrade avoided · by choosing the right building

A move is a hundred small projects that all have to land in the same week. The work is keeping them on one page.

One command center for the whole move
  1. 1Plan
  2. 2Track
  3. 3Log
  4. 4Budget
  5. 5Decide

The challenge

The old building was about twice the size the business needed, with a lease that still had a year to run. A new, better building was available, with incentives that only existed if the company moved inside the landlord’s window. Staying was not free: waiting meant more rent on unused space, then a decision at market rates with none of the incentives. Orders had to keep going out, with only one short, planned pause, and leadership needed to know, every week, whether the move still made financial sense.

Our approach

We ran the move from one Smartsheet command center, so nobody finds out about a problem on moving day. We also built the board view of the move’s economics from the same budget tracker, and racking, network, and offices came online in sequence, tracked day by day.

The plan split the move into lanes, so each vendor’s work landed in one place

  • Racking down in one building, up and inspected in the other

    Warehouse lane: rack inspection and release, then shipping restarts

  • Power, network, servers and security live before shipping restarted

    Office and IT lane: server power circuit, network, Wi-Fi and scanners

  • Build-out, movers and storage each had their own email thread

    Three lanes: building and lease, warehouse and product, office and IT

Client
National consumer wellness products company
Scope
Warehouse and office relocation, from lease to final inspection
Platform
Smartsheet · Dashboards · Reports · RAID log · Budget tracker
Users
CFO · Operations · Warehouse · IT · Vendors and contractors
Status
Complete

The numbers that matter came first, and each week’s decisions sat on one page

  • Days to handback

    4

  • Days to rack sign-off

    9

  • Open critical-path items

    6

  • Past due

    0

Each week, the CFO saw the two or three calls that needed an answer, with the cost of waiting spelled out, like the sample decisions here. Simplified illustration.

Sample decisions for the week

  • Approve the construction contract once the price is confirmed
  • Confirm temporary storage during build-out
  • Drop exit repairs once the landlord confirms in writing

The same command center fits any project with too many vendors and a hard date

  • Warehouse and plant relocations
  • Office moves and new site openings
  • Equipment installs
  • Any operation that has to change underneath itself without stopping

One plan. One budget. One honest weekly view.