Case study · Portico Group · For manufacturing operations leaders
Short Kaizen events with the floor team cut assembly time at an equipment maker.
44% smaller: the seal cell area, and nearly all of the remaining time is value-added work
85% to 66%: non-value-added time on the grinder line, as mapped in the value stream
Everyone trained: stockroom, paint, assembly, QC, and shipping learned the new flow together
- grinder assembly labor
- −30%
- grinder assembly labor · per grinder
- travel distance
- −33%
- travel distance · for parts and grinders
- faster grinder turnaround
- 1–2 days
- faster grinder turnaround · painting in one pass
- seal assembly cycle time
- −40%
- seal assembly cycle time · per seal
So we didn’t start with a big program. We started with two focused Kaizen events, with the people who actually do the work.
The challenge
The company was “idea-rich and resource-poor.” Everyone knew where the waste was. Nobody had the bandwidth to fix it. Leadership wanted continuous improvement, but a few hard years, thin bandwidth, and few champions had kept it on the wish list.
Our approach
Each event brought together the people who actually do the work: assembly, paint, stockroom, engineering, and operations. We mapped the value stream first, then changed the flow on the floor: castings painted fully in one pass and staged where assembly uses them, and batch seal assembly replaced with a compact cell and gravity-flow racks fed by Kanban. Basic automation on the hydraulic press freed the operator to keep assembling while it cycles.
Repainting kept grinders waiting, and moving around the plant
- Some grinders went back to paint a third time, after the drive was installed
- Every coat meant at least one night of drying, sometimes three
- Parts and grinders traveled 1,480 feet, about a quarter mile
- Moving heavy grinders was one of the riskiest jobs in the plant
- Client
- Wastewater equipment manufacturer
- Events
- Kaizen 1: Painted parts Kanban · Kaizen 2: Seal assembly cell
- Methods
- Value stream mapping · Kanban · One-piece flow · Standard work
- Timeline
- Two 4-day events
The fixes took the waiting out of grinder and seal assembly
Standard work set clear steps for sandblasting and painting, handling painted parts, capturing labor, and issuing material to work orders.
Both Kaizens cut the time it takes to build
The seal assemblers started the week wanting to keep things as they were, with little confidence the change would work. By the end, they were helping drive it, and believed in the new way.
That’s the tipping point toward a Kaizen culture.
Related case studies
- −45%Lead time reduction plus a 30% gain in labor efficiency, within 10 weeks of kickoff.Lean transformation · Custom transformer manufacturer · US/Mexico
- +50%On-time delivery with 30% more production capacity, no added headcount or capital equipment, plus another 30% projected from a new facility layout.Supply chain assessment · Bolted steel tank manufacturer
- 2×Year-over-year growth supported by operations and supply chain work, with 10%+ supplier savings plus 3–5% in rebates.Pet nutrition · PE-backed fresh pet food company